PUC §8372: (a) Within 180 days of the first request from a customer or developer to establish a microgrid, the governing board of a local publicly owned electric utility shall develop and make available a standa
Read the full statutory text
(a) Within 180 days of the first request from a customer or developer to establish a microgrid, the governing board of a local publicly owned electric utility shall develop and make available a standardized process for the interconnection of a customer-supported microgrid, including separate electrical rates and tariffs, as necessary. The separate rates and tariffs shall not compensate a customer for the use of diesel backup or natural gas generation, except as either of those sources is used pursuant to Section 41514.1 of the Health and Safety Code, or except for natural gas generation that is a distributed energy resource. (b) The governing board shall ensure the microgrid rates and charges do not shift costs to, or from, a microgrid customer or nonmicrogrid customer, and shall ensure each microgrid and its components comply with the local publicly owned electric utility’s applicable regulatory requirements.
Verify at the official source: California legislative text
Facing this? Know exactly what happens next.
MOFRD turns this code section into your situation: the deadlines that apply to you, the forms your county uses, and the resolution paths people in your position actually take. Free for 3 days — no card required.
This page is legal information, not legal advice. Code text is sourced from official publications and may lag amendments — always confirm at the official source linked above. Plain-English summaries and relationship data are AI-derived and reviewed on an ongoing basis; verify with a licensed attorney before acting.