PCC §10848: If the control of a contractor is terminated or he or she abandons the work, and the work is performed by day’s labor or informal contract as provided in Section 10845, he or she is not entitled to re
Read the full statutory text
If the control of a contractor is terminated or he or she abandons the work, and the work is performed by day’s labor or informal contract as provided in Section 10845, he or she is not entitled to receive any portion of the amount to be paid under the contract until it is fully completed. After completion, if the unpaid balance exceeds the sum of the amount expended by the state in finishing the work, plus all damages sustained or to be sustained by the state, the excess not otherwise required by law to be retained shall be paid to the contractor, but if such sum exceeds the unpaid balance, the contractor and his or her surety are liable to the state for the excess. If the surety completes the contract work, as provided in Section 10845, such surety shall be subrogated to money due under the contract and to money which shall become due in the course of completion by the surety, to the extent provided by law.
Verify at the official source: California legislative text
Facing this? Know exactly what happens next.
MOFRD turns this code section into your situation: the deadlines that apply to you, the forms your county uses, and the resolution paths people in your position actually take. Free for 3 days — no card required.
This page is legal information, not legal advice. Code text is sourced from official publications and may lag amendments — always confirm at the official source linked above. Plain-English summaries and relationship data are AI-derived and reviewed on an ongoing basis; verify with a licensed attorney before acting.