California · Civil Code

CIV §9362: (a) Not later than 10 days after each of the following events, the public entity shall give notice to a claimant that has given a stop payment notice of the time within which an action to enforce paym

What this law says, in plain English

A public entity must notify a claimant who filed a stop payment notice within 10 days, informing them of the timeframe for taking legal action to enforce payment.

Read the full statutory text
(a) Not later than 10 days after each of the following events, the public entity shall give notice to a claimant that has given a stop payment notice of the time within which an action to enforce payment of the claim stated in the stop payment notice must be commenced: (1) Completion of a public works contract, whether by acceptance or cessation. (2) Recordation of a notice of cessation or completion. (b) The notice shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1. (c) A public entity need not give notice under this section unless the claimant has paid the public entity ten dollars ($10) at the time of giving the stop payment notice.

Verify at the official source: California legislative text

Facing this? Know exactly what happens next.

MOFRD turns this code section into your situation: the deadlines that apply to you, the forms your county uses, and the resolution paths people in your position actually take. Free for 3 days — no card required.

This page is legal information, not legal advice. Code text is sourced from official publications and may lag amendments — always confirm at the official source linked above. Plain-English summaries and relationship data are AI-derived and reviewed on an ongoing basis; verify with a licensed attorney before acting.