PCC §10261.5: (a) Any state agency which fails to make any progress payment within 30 days after receipt of the payment request from a contractor on a construction contract for an undisputed payment request, which

What this law says, in plain English

A state agency must make progress payments to construction contractors within 30 days of receiving an undisputed payment request.

Read the full statutory text
(a) Any state agency which fails to make any progress payment within 30 days after receipt of the payment request from a contractor on a construction contract for an undisputed payment request, which was properly submitted by the contractor to the agency, shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure. Any state agency which independently calculates the amount due on a progress payment and which fails to make a progress payment within 30 days of the first submittal of the estimate for each contract by the engineer, shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure. In the event that the payment is not made within 30 days of receipt of the contractor’s request or the first submittal by the engineer, and the Controller has processed the payment within 14 days of receipt of the request or submittal, the contracting state agency shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure. In the event that the payment is not made within 30 days of receipt of the contractor’s request or the first submittal by the engineer, and the contracting state agency has processed the payment within 16 days after receipt of the request or submittal, the Controller shall pay interest as provided in Section 685.010 of the Code of Civil Procedure. For purposes of this section, a payment request shall be considered properly executed if funds are available for payment of the payment request, and payment is not delayed due to an audit inquiry by the Controller. (b) Upon receipt of a payment request, each agency shall require: (1) That each payment request be reviewed as soon as practicable after receipt for the purpose of determining that a payment request is a proper payment request. (2) Any payment request determined not to be a proper payment request suitable for payment shall be returned as soon as practicable, but not later than seven days, after receipt, specifying the reasons that the payment request is not a proper payment request. (3) The number of days available to a state agency to make a timely payment of payment request without incurring interest shall be reduced by the number of days by which an agency exceeds the requirements of paragraph (2).

Verify at the official source: California legislative text

Facing this? Know exactly what happens next.

MOFRD turns this code section into your situation: the deadlines that apply to you, the forms your county uses, and the resolution paths people in your position actually take. Free for 3 days — no card required.

This page is legal information, not legal advice. Code text is sourced from official publications and may lag amendments — always confirm at the official source linked above. Plain-English summaries and relationship data are AI-derived and reviewed on an ongoing basis; verify with a licensed attorney before acting.